https://phynvesting.substack.com/p/part-2-the-turbine-the-market-left?open=false#§chapter-5-the-brawl-of-bloom-vs-capstone Didn't understand this part (grey box) that starts with: Consider a 10MW data center. Cooling is 40% of total facility power, so if compute is 60% of total draw, 6.67MW is needed for cooling... He then continues how BE is at a disadvantage because it needs to pull 2.82MW from grid for cooling. Why don't they just add additional BE boxes that create this 2.82MW electricity just for cooling. Still would require only 20MW of gas inputs then for BE vs 30.3MW for CGEH. I am not an expert! Can someone correct my thinking.